WCS PLACES SPENT FUEL APPLICATION ON HOLD

By letter dated mid-April 2017, Waste Control Specialists (WCS) asked the U.S. Nuclear Regulatory Commission (NRC) to temporarily suspend the agency’s review of its application to construct and operate a spent nuclear fuel Consolidated Interim Storage Facility (CISF) in Andrews County, Texas.

WSC “is faced with a magnitude of financial burdens that currently make pursuit of licensing unsupportable,” Rod Baltzer, the company’s President and CEO, said in a letter to the NRC dated April 16, 2017.  According to Baltzer, the estimated $7.5 million that is needed to continue the licensing process was a significant factor in WCS’ decision.  The following day, NRC announced that it would freeze the review.

The request comes as EnergySolutions is trying to buy WCS, although the U.S. Department of Justice has sued to block the merger, arguing it would essentially create a monopoly on radioactive waste disposal.  “WCS expects to go forward with this project at the earliest possible opportunity after completion of the sale,” Baltzer said in a statement.

In the meantime, on March 16, 2017, the U.S. Nuclear Regulatory Commission (NRC) announced that the agency was providing additional opportunities for the public to comment on the CISF application that was submitted by WCS.

Overview

NRC’s review would proceed on two parallel tracks—one on safety issues and the other on environmental issues.  Both the safety and environmental reviews must be completed before the NRC makes a final licensing decision on the application.

In a letter to WCS dated January 26, 2017, the NRC set a schedule for its safety and environmental reviews.  The schedule sets a target of making a licensing decision by the third quarter of fiscal year 2019—assuming that WCS provides high-quality responses, on schedule, to any NRC requests for additional information.

The NRC’s letter to WCS is available on the agency’s website at https://www.nrc.gov/docs/ML1701/ML17018A168.pdf

Public Meetings

The NRC held the following two public meetings near the site of the proposed CISF to take public comments on the scope of the environmental review:

  • Hobbs, New Mexico:  Lea County Event Center (5101 N. Lovington Highway) from 7:00 – 10:00 p.m. MT on February 13, 2017
  • Andrews, Texas:  James Roberts Center (855 TX-176) from 7:00 – 10:00 p.m. CT on February 15, 2017

On April 6, 2017, NRC staff hosted an additional public meeting at the agency’s headquarters in Rockville, Maryland so members of the public can ask questions of NRC staff and present oral comments.  The meeting, which was webcast, was held from 7:00 – 10:00 p.m.  It was held in the Commissioners’ Conference Room at One White Flint North, which is located at 11555 Rockville Pike in Rockville, Maryland.

Information about the public meetings will be posted to the NRC public meetings schedule on the agency’s website at www.nrc.gov.

Submitting Comments

The NRC will now take comments on the scope of its Environmental Impact Statement (EIS) on the proposed facility through April 28, 2017.  Interested stakeholders can submit comments for the CISF as follows:

  • Federal Rulemaking Website: Electronic provide comments at regulations.gov
  • Mail:  Send comments to Cindy Bladey, Office of Administration, Mail Stop: OWFN-12 H08, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001

Written comments should refer to Docket ID NRC-2016-0231.

Background

On April 28, 2016, WCS filed an application seeking a 40-year license for a CISF to receive spent fuel from nuclear reactors for storage, pending final disposal.  (See LLW Notes, May/June 2016, pp. 16-17.)  Specifically, WCS is requesting authorization to construct and operate a CISF at the company’s 60.3 square kilometer (14,900 acre) site in western Andrews County, Texas.  On this site, WCS currently operates facilities that process and store certain types of radioactive material—mainly low-level radioactive waste and mixed waste.  The facility also disposes of hazardous and toxic waste.

According to the application, WCS plans to construct the CISF in eight phases.  Phase one of the CISF would be designed to provide storage for up to 5,000 metric tons uranium (MTU) of spent nuclear fuel received from commercial nuclear power reactors across the United States.  WCS proposes that small amounts of mixed oxide spent fuels and Greater-Than-Class C (GTCC) low-level radioactive wastes also be stored at the CISF.  WCS stated that it would design each subsequent phase of the CISF to store up to an additional 5,000 MTU.  A total of up to 40,000 MTU would be stored at the site by the completion of the final phase.  Each phase would require NRC review and approval.

WCS would receive canisters containing spent nuclear fuel from the reactor sites.  Once accepted at the site, WCS would transfer them into onsite dry cask storage systems.  WCS plans to employ dry cask storage system technology that has been licensed by the NRC pursuant to 10 CFR Part 72 at various commercial nuclear reactors across the country.  According to WCS, the dry cask storage systems proposed for use at the CISF would be passive systems (i.e., not relying on any moving parts) and would provide physical protection, containment, nuclear criticality controls and radiation shielding required for the safe storage of the spent nuclear fuel.  WCS also states that the dry cask storage systems would be located on top of the concrete pads constructed at the CISF. 

For additional information, please contact Maureen Conley of the U.S. Nuclear Regulatory Commission at (301) 415-8200.